Friday, June 5, 2026
During the week of June 8, crews will work in the following areas:
- Clarkson Street, between Colfax and 14th avenues
- Natural gas line installation
- Full road closure, follow posted detours
- Parking restrictions
- Intersection of Colfax Avenue and Clarkson Street
- Nightwork: Friday, June 12 through Tuesday, June 16 from 7 p.m. to 5 a.m.
- Natural gas line installation
- Utility locates activities
- Full intersection closure, follow posted detours
- Parking restrictions
Crews will work Monday through Friday from 7 a.m. to 5 p.m. In certain circumstances, crews may work evenings, nights or weekends.
Schedules are subject to change.