Updates
Learn about our current work areas
Home > Updates
Friday, July 24, 2026
During the week of July 27, crews will work in the following areas:
- Intersection of 16th Avenue and Clarkson Street
- Natural gas line installation.
- Weekend work Saturday, July 25 and Sunday, July 26
- Full intersection closure, through traffic follow posted detours
- Clarkson Street between Colfax and 17th avenues will temporarily operate as a two-way street to maintain local access
- Parking restrictions
- Clarkson Street, between 17th and 18th avenues
- Natural gas line installation
- Natural gas service line installation
- 24/7 single lane closure, through traffic allowed
- Parking restrictions
- Equipment and materials staged overnight
- Intersection of 18th Avenue and Clarkson Street
- Natural gas line installation.
- Weekend work Saturday, August 1 and Sunday, August 2
- Shifting lane closures, through traffic allowed
- Parking restrictions
Crews will work Monday through Friday from 7 a.m. to 5 p.m. In certain circumstances, crews may work evenings, nights or weekends.
Schedules are subject to change.
This map is a graphic and may not show exact locations